Programme and methodology were vital to the whole approach and were the major drivers throughout the design process.
After completion of design with the architects we ran through the calculations with our structural engineer to ensure everything designed was fit for purpose.
Q-RAL base channel was installed directly into our structural steel, removing any deflection.
Just 42 Hours before opening of the restaurant, an external bespoke triple glazed unit was damaged. Glass Structures Limited sent their operatives to site on an evening to remove the damaged unit. As only one pane was broken, the unit was taken back to our factory in Barking and was changed, enabling the team to re-install later the next evening.